(c) The adjusting unit prices shall be the arithmetic average of the weekly or monthly prices of each applicable economic indicator only for the period specified under the “Adjusting Unit Price” column shown in paragraph (b) immediately preceding the effective date the option term is exercised.
(d) An established market price is a price that is established in the course of ordinary and usual trade between buyers and sellers free to bargain and that can be substantiated by data from sources independent of the offeror(s); and the net price after applying any standard trade discounts offered by the Contractor. The established market price under this clause may reflect industry-wide and/or geographically based market price fluctuations for commodity groups or specific supplies. The established market price that shall be used for the MRE items subject to price adjustments under this clause, and the economic indicators and publications to be used are listed in paragraph (b) of this clause.
(1) The base unit prices for the purpose of the adjustment calculations under this clause shall be the arithmetic average of the weekly or monthly prices of each applicable economic indicator only for the period specified under the “Base Unit Price” column in paragraph (b) immediately preceding (i) the closing date for proposals, if no discussions are held, (ii) the due date for final proposal revisions, if discussions are held, or (iii) the opening date, if sealed bidding is used.
(2) The adjusting unit prices shall be the arithmetic average of the weekly or monthly prices of each applicable economic indicator for the period specified under the “Adjusting Unit Price” column in paragraph (b) immediately preceding the effective date the option term is exercised, except for linerboard which shall require one additional adjustment six months after each option term is exercised.
(e) With respect to increases or decreases under this clause, no adjustment shall be made to the base term contract unit prices. One adjustment calculation shall be made annually to determine the unit prices applicable to the forthcoming option term (if exercised), except linerboard which will be adjusted on a semi-annual basis.
(f) EPA ALLOWANCE FACTOR: For the purpose of price adjustment pursuant to this clause, it shall be conclusively presumed that the amount shown under “Portion Subject to EPA” represents the cost of each item that is subject to adjustment. The portion subject to EPA refers to the element of cost for each item that is outside the control of the vendor and in “Schedule B” the offerors will be required to fill in this amount. This is the only portion of the cost that will be subject to the EPA provision. The EPA provisions based on changes in market prices for product material costs such as beef, chicken, and pork are subject to the EPA, because there is serious doubt concerning the stability of market conditions. The balance of product costs for items such as labor, overhead, General and Administrative (G&A), transportation, and profit are those contingencies that can be included in the contract price and can be identified and covered separately through firm fixed prices. The EPA allowance factor remains fixed throughout the life of the contract unless a Government authorized change is made to the contract which affects this allowance.
(g) PERFORMANCE REQUIREMENTS: The United States Army Research, Development and Engineering Command (RDECOM) Natick Soldier Center (NSC) who prepares the specifications has moved from Military Specifications to Performance Requirements. The Government no longer states the specific amount of product (meat, potatoes, gravy, etc) that goes into a MRE, only an overall amount with a protein and carbohydrate requirement. Meeting the protein requirement indicates that the contractor has put in sufficient (meat) quantities in the MRE to satisfy the requirement. (Different contractors will put in differing quantities of beef, pork, chicken breast, etc. to meet the protein performance requirements). This is why specific weights or quantities cannot be specified in advance in this EPA as would be used in a Military Specification and the cost for the items subject to adjustment will be entered by the contractor in Section B. The Government performs oversight to ensure that the performance requirements are met or exceeded.
(h) Adjustments shall be calculated as follows: (Round to four decimal places)
(1) Compute the Adjusting Unit Price and the Base Unit Price.
(2) (Adjusting Unit Price - Base Unit Price)/Base Unit Price = Market Price Change (+ or -).
(3) Market Price Change X Allowance Factor = Contract Unit Price Adjustment (+ or -) for
each item subject to EPA adjustment.
(4) The original option unit price(s) for each option will be the sum of the firm fixed price portion and the portion subject to the EPA (Allowance Factor). The adjusted unit price(s) for each option shall be determined by increasing or decreasing (as appropriate) the Allowance Factor by the Contract Unit Price Adjustment and adding that to the firm fixed price portion agreed to at the time of award for the option period being adjusted.
(5) Determine the Contract Price Adjustment by computing the sum total of the price adjustment of all items subject to EPA.
(i) Price adjustments pursuant to this clause shall be made by contract modification showing the calculations used to derive the adjusted contract unit price.
(j) PAYMENTS: Payment for items pending adjustment under this clause shall be at the existing unadjusted contract unit price until an adjustment modification has been issued. Following issuance of an adjusting contract modification, the Government shall pay the Contractor, upon submission of proper invoices or vouchers, the adjusted price stated in the contract modification for the applicable option period. The contractor represents by submitting its final invoice that the total amount billed under this contract reflects all increases or decreases required or authorized by this clause.
(k) Any pricing actions pursuant to the “CHANGES” clause or other provisions of the contract will be priced as though there were no provisions for economic price adjustment.
(l) No adjustment will be made under this clause unless the total change in the contract amount is $500.00 or more.
(m) UPWARD CEILING ON ECONOMIC PRICE ADJUSTMENT: The total increase in any contract unit price shall not exceed 10% per annum of the original option unit prices agreed to at time of award. There is no percentage limit on downward adjustments under this clause.
(n) REVISION OF MARKET PRICE INDICATOR: In the event (i) any applicable market price indicator is discontinued or its method of derivation is altered substantially or (ii) the Contracting Officer determines that a particular market price indicator consistently and substantially no longer reflects market conditions, the parties shall mutually agree upon an appropriate and comparable substitute and the contract shall be modified to reflect such substitute effective on the date the indicator was discontinued, altered, or began to consistently and substantially fail to reflect market conditions.
(o) DISPUTES: If the parties fail to agree on an appropriate substitute market price indicator or implementation of other matters addressed by this EPA clause then the matter shall be resolved in accordance with the DISPUTES clause of the contract.
(p) AUTHORITY TO ADD ADDITIONAL ITEMS TO THIS CLAUSE: Paragraph (b) of this clause identifies 24 unique components contained in the MRE Assembly. These components are selected based on historical data and may not be included in every assembly. Refer elsewhere in the solicitation/contract for listing of the exact component makeup. Due to customer requirements, the contracting officer may add additional components to the assembly. The contracting officer will show within paragraph (b) the additional components(s).
(q) EXAMINATION OF RECORDS: The Contractor agrees that the Contracting Officer or designated representative shall have the right to examine the Contractor’s books, records, documents, or other data the Contracting Officer deems necessary to verify Contractor adherence to the provisions of the clause.
(r) In the event any applicable market price indicator is not published for any week(s), that week will not be included in calculating the base unit price or the adjusting unit price as applicable. For instance, if within a 52 week period an indicator is not published 4 times, the average of the 48 published prices only will be calculated. When a range of prices is provided, for the purposes of the calculations the arithmetic average of the high and low number will be calculated to determine the indicator for that period.
(End of Clause)