As prescribed in 16.203-4-90(k), use the following clause when the contractor will propose a material index for use in the economic price adjustment clause.
52.216-9028 ECONOMIC PRICE ADJUSTMENT LABOR AND MATERIAL (FEB 2009)
TO BE COMPLETED BY CONTRACTOR
MATERIAL PROPOSED FOR ECONOMIC PRICE ADJUSTMENT
The following types of materials and labor, if applicable, are subject to price adjustment pursuant to FAR Clause 52.216-4, Economic Price Adjustment(Section I), included herein:
TYPES OF MATERIAL DIRECT COST PER TYPES OF RATE OF PER UNIT OF
MATERIAL PRICES UNIT OF PROCUREMENT LABOR PAY ROCUREMENT
(END OF CLAUSE)